14.11.2024
Planning permission granted for the “Brandscheid A60” solar park.
The planned “Brandscheid A60” ground-mounted photovoltaic plant has reached an important milestone:
Planning permission has been granted for the 9.6 MWp project. This marks the successful completion of the approval process and now enables the start of the construction phase.
Project section | Status |
---|---|
Regional planning examination | |
Grid connection commitment | |
Species protection survey / environmental report | |
Building application procedure, urban land use planning procedure | |
Project takeover by investor/operator | Kintlein & Ose |
Building permit | |
Expected commissioning | Q4/2025 |
The project, which was taken over by Kintlein & Ose GmbH & Co. KG in February 2023, is located on the verge of the A60 motorway in an agriculturally disadvantaged area of the local community of Brandscheid in the Eifel district of Bitburg-Prüm.
In accordance with the agreement with Kintlein & Ose, MK solutions & consulting will carry out the construction management procedure and accompany the further project development until commissioning.
Commissioning of the solar park is planned for the fourth quarter of 2025. The electrical energy generated is fed into the grid via a regional transformer station.